DQR ID | Subject | Data Streams Affected |
---|---|---|
D040907.1 | SGP/SIRS/C1/E13 - Incorrect calibration coefficients | sgpsirsC1.00, sgpsirsC1.b1, sgpsirsE13.00, sgpsirsE13.b1, sgpsirs20sC1.a0, sgpsirs20sE13.a0 |
D060630.21 | SGP/SIRS/E13 - Reprocess: Longwave Calibration error | sgpsirsE13.b1 |
Start Date | Start Time | End Date | End Time |
---|---|---|---|
08/27/2004 | 1830 | 09/07/2004 | 2130 |
Subject: | SGP/SIRS/C1/E13 - Incorrect calibration coefficients |
DataStreams: | sgpsirsC1.00, sgpsirsC1.b1, sgpsirsE13.00, sgpsirsE13.b1, sgpsirs20sC1.a0, sgpsirs20sE13.a0 |
Description: | After the DIR changeout on 8/27, the DLH measurements at the central facility vary significantly between pyrgeometers by as much as 65 Wm^(-2). It was discovered that the two downwelling pyrgeometers destined for C1 and E13 may have been swapped during installation. The instrument mentor is unsure of applied calibration coefficients during this DQR's time period. Backing out new downwelling longwave irradiances would be difficult in this case. Fortunately, the problem period is less than a fortnight. |
Measurements: | sgpsirsE13.b1:
sgpsirsC1.b1:
sgpsirsC1.00:
sgpsirs20sE13.a0:
sgpsirs20sC1.a0:
sgpsirsE13.00:
|
Start Date | Start Time | End Date | End Time |
---|---|---|---|
12/11/2003 | 1935 | 02/16/2006 | 1905 |
Subject: | SGP/SIRS/E13 - Reprocess: Longwave Calibration error |
DataStreams: | sgpsirsE13.b1 |
Description: | Modified pyrgeometer calibration procedures were implemented beginning in December 2003. These modified procedures introduced a calibration bias in the longwave data. The previous procedures were re-implemented at all sites between December 2005 and February 2006 to restore proper calibrations. The data collected while the incorrect procedures were in place are being reprocessing to remove the calibration bias. Note, this also affected standard deviation, maximum and minimum data fields. |
Measurements: | sgpsirsE13.b1:
|