Start Date | Start Time | End Date | End Time | Data Quality Metric |
---|---|---|---|---|
11/01/1998 | 0000 | 11/19/1998 | 2359 | Suspect |
Subject: | TWP/C2 Installation |
DataStreams: | twpmfrsrC2.00, twpmfrsrC2.a1, twpmfrsrC2.a0, twpmfrsrC2.b1 |
Description: | The Nauru ARCS was installed during the period September-November 1998. Data were being collected by the end of October, but for the first several weeks of November, the site was undergoing considerable change, so data from that period should be used with caution. The official site dedication occured on November 20. Most on-site activity ended following the dedication so we will consider November 20 to be the beginning of the Nauru operations. The last members of the installation team left Nauru on November 24. |
Suggestions: | |
Measurements: | twpmfrsrC2.a1: more
twpmfrsrC2.00: more twpmfrsrC2.a0: more twpmfrsrC2.b1: more |